Project Details:

Total Value:     $170 000
Year Completed:    2017
Duration:     5 months

Background:

The project involved the design and supply of multiple pontoons for pumping operations, delivering water from various dams to the process plant at the mine in Lesotho.

Description:

MKDesigns designed, fabricated, and supplied four distinct pontoons for the mine. Each pontoon was equipped with Warman 8-6 pumps. The scope of supply also included floating walkways, 12-inch hoses, and hose floats to support the pumping operations.