Water Test Facility Waste Water Transfer
Project Details:
Total Value: $165 000
Year Completed: 2023
Duration: 6 months
Background:
There was a requirement to transfer the waste water from the water test facility to the effluent plant at the paintshop.
Description:
A pipe route through the production facility was planned and the hydraulic design done. A 50mm galvanised pipeline was installed over a distance of approximately 0.5 km. Two pumps with bag filters were installed operating on a standby and duty pump principle.