Pontoons
Project Details:
Total Value: $170 000
Year Completed: 2017
Duration: 5 months
Background:
The project involved the design and supply of multiple pontoons for pumping operations, delivering water from various dams to the process plant at the mine in Lesotho.
Description:
MKDesigns designed, fabricated, and supplied four distinct pontoons for the mine. Each pontoon was equipped with Warman 8-6 pumps. The scope of supply also included floating walkways, 12-inch hoses, and hose floats to support the pumping operations.